Disaster Information Respond & Recover Tool

Project Recruitment Report

This is a list of available disaster recovery projects.

The cost for these projects have already been funded by generous donations.

Volunteers to complete the work is all that is needed,
but any and all donations are appreciated for other unfunded projects.

Thank you for your consideration in volunteering on one of these projects.
To help a disaster survivor recover please register online www.dirrt-ok.org.

Printer-friendly versionPrinter-friendly version

ID Location Priority (1=Urgent)sort descending Work Description Number of volunteers needed Number of Days for volunteers to complete job Date project added to list
194792 - Adba Moffett 1 House has been completely mucked-out. Need to install new floor joists, subfloor, finished flooring, plumbing, electrical, insulation, drywall, cabinets and fixtures 10 40 01/09/2020
195294 - Kshe Tonkawa 1 Skylight was replaced but is still having some leaking issues with the roof on the west area above the entrance and along the east where add-on meets original home. Roof needs two coats of elastomeric coating and and elasto tape put over any areas where there might be holes or seams. Minor drywall repairs that just involve taping and some texturing. Roof will need to be done before interior repairs. 6 1 03/03/2020
200176 - Tcle Talala 1 Repair metal roof leek at add-on by removing metal, replacing rafters and decking, then reinstalling metal. When metal is re-installed apply expanding seal tape near where roof meets main structure of the mobile home. Hang R-19 insulation and drywall on the ceiling and then tape, bed and texture. 5 3 05/13/2020
202679 - Dmor Ponca City 1 The roof will need to be removed and replaced as well as any rotted decking. A window will need to be trimmed out with cedar trim and caulked. Remove carpet padding and buckled hardwood floor down to the subfloor. Install tar paper, new subfloor then vapor barrier and new laminate flooring then trim to finish out the room. 10 7 06/11/2020
201669 - Jmos Chelsea 2 Remove and replace roof area over living room. Repair bathroom and bedroom ceiling drywall then mud, tape, and paint. 4 4 06/22/2020
193485 - Tham Cleveland 3 Licensed electrician needs to inspect and replace any faulty wiring, licensed plumber needs to replace plumbing that has been removed and fix the new plumbing that has been done improperly. Furnace ductwork installed throughout house, house raised so that footings and pilings can be installed, install insulation under the floor, install missing floor joists at 16” on center through majority of house, install subfloor through entire house, install insulation in walls, hang drywall on walls (the muck out removed it up to 4’ but additional drywall has been removed up to the ceiling in places), install trim around windows, doors, and floor; install kitchen cabinets, and paint the drywall and trim. Homeowner has purchased all materials needed for repair. 6 15 12/02/2019
197061 - Swil Tulsa 3 Install 18 - 12 ft pieces of k-pattern stain grade trim for base and casing around doors. Apply one gallon of stain and poly and one gallon of white paint on the trim in the closets. Stain the new trim and touch up existing trim. Tools needed are finish nailer and a miter saw. Homeowner has SBA funding for materials. 3 2 01/06/2020
191009 - Esmi Moffett 3 Muck-out ceiling. After electrical and plumbing have been completed by contractors the sub floor will need to be replaced and any floor joists fixed. After the sub floor is replaced, the walls can be insulated and drywall can be hung on the walls and ceilings and then taped, bedded and textured and painted. Upon the completion of the walls and ceiling, new flooring can be installed throughout the home and new tile floors installed in the bathrooms. New interior doors and exterior doors will need to be replaced along with base cabinets, vanities and base and door trim. 10 25 01/09/2020
190758 - Tjoh Sand Springs 4 Completion of interior stair trim. 01/17/2020
199027 - Amcg Tulsa 4 All insulation in the basement ceiling will need to be removed and shockwave applied to the exposed subfloor and floor joist. The basement will also need to be power washed and cleaned of mud and other contents. Once the basement is prepped and dried out, insulation will need to be installed between floor joists and then covered with 6mm plastic sheething. Hydraulic cement needs to be applied to all cracks on the walls and floor. Once hydraulic cement has set the walls and floors will need to be coated with basement sealer. At least two coats need to be applied. 4 3 02/04/2020
190886 - Vhar Fort Gibson 4 Finish install of drywall in garage then tape and mud. Build shelves in laundry room closet. Caulk above kitchen cabinets and touch up paint. 4 5 03/17/2020
190962 - Rall Skiatook 4 Remove and replace tile and drywall on walls in the bathroom and behind the shower replace hardie backer. Replace drywall in hotwater tank closet. Install kitchen cabinets, counter-tops, two exterior doors, four lights and 1 ceiling fan. Any evidence of mold will need to be removed and treated with mold inhibitor. 5 5 03/17/2020
201393 - Cfre Webbers Falls 4 Complete texturing, install laminate flooring, trim, and paint 3 rooms. Hang 4 doors. Install ceramic tile in the laundry room area. Apply roofing tar to stop leak on a valley on the add-on portion 6 5 05/13/2020
200251 - Bdic Nowata 4 Install new drop ceiling tiles in living room. Replace damaged drywall and insulation in the south room. Other bedrooms have water spots that need to coated with kilz. Contractor replacing roof. 3 2 05/26/2020
191011 - Jmic Moffett 4 Paint 5 3 07/10/2020
201740 - Vyou Kingfisher 4 Two areas in the ceiling have damage that need to be removed along with the insulation. Replace with new insulation drywall, tape, bed, and textured. 4 3 07/10/2020
204530 - Lmor Chelsea 4 Remove old flooring in back room and replace sub floor. Remove paneling, replace sheathing behind and reinstall paneling. Lay new laminate floor. 5 5 07/10/2020