Disaster Information Respond & Recover Tool

Project Recruitment Report

This is a list of available disaster recovery projects.

The cost for these projects have already been funded by generous donations.

Volunteers to complete the work is all that is needed,
but any and all donations are appreciated for other unfunded projects.

Thank you for your consideration in volunteering on one of these projects.
To help a disaster survivor recover please register online www.dirrt-ok.org.

Printer-friendly versionPrinter-friendly version

ID Location Priority (1=Urgent)sort descending Work Description Number of volunteers needed Number of Days for volunteers to complete job Date project added to list
191054 - Clam Grove 1 Install insulation, drywall, tape, mud, and texture. Install subfloor, vanities, cabinets, and counter top. Paint, install flooring, doors, and trim. 01/09/2020
191067 - Lhes Yukon 1 Build a 40 ft ramp for a wheel chair with a switch back ramp that begins near her current porch and has a landing on the north side where you turn and go back to the south towards the existing porch. Homeowner can not safely access or leave her home until this ramp is built 7 2 02/17/2020
193729 - Vfre Sapulpa 1 Demo front part of roof, the 6/12 section. Replace decking and reshingle that portion of roof. Repair water damaged drywall in living room. Replace damaged insulation. Repair ceiling in kitchen. Spray Shockwave on any mold found. 5 5 02/24/2020
195294 - Kshe Tonkawa 1 Skylight was replaced but is still having some leaking issues with the roof on the west area above the entrance and along the east where add-on meets original home. Roof needs two coats of elastomeric coating and and elasto tape put over any areas where there might be holes or seams. Minor drywall repairs that just involve taping and some texturing. Roof will need to be done before interior repairs. 6 1 03/03/2020
196028 - Sbro Blackwell 1 Paneling and all sheetrock in living room will need to be removed and replace along with insulation on the exterior walls. Three bedrooms will need to have the sheetrock cut up 4 feet from the floor and replaced, taped, bedded and painted. NE bedroom will need to have some subfloor removed and replaced and new laminate flooring installed once subfloor is replaced. Bathroom is a total loss. Any remaining sheetrock will need to be removed as does the damaged subfloor. New tub, plumbing lines and fixtures including toilet, sink and faucets need installed. A tile surround will need to be installed above tub to the ceiling and tile will need to installed on floor. Prior to tile being installed on the floor and tub surround vols will need to coat the sheetrock and subfloor with Red Guard water proofing. All wood trim in the home will need to salavaged, labeled and re-used. Proper PPE (i.e. masks, tyvek suits) will be needed. Once sheetrock is removed the studs, floors and other exposures will need to be sprayed with Shockwave and allowed to dry. 10 14 03/03/2020
199031 - Cwal Sand Springs 1 Remove and replace any roof decking that is damaged and install new shingles. 12 5 03/17/2020
197331 - Afow Hinton 2 Replace roof and areas of rotted decking. 10 5 02/17/2020
190886 - Vhar Fort Gibson 2 Finish install of Hardie siding on a small section of the front and back side of the home and back porch. Install small section of OSB and house wrap near the back porch. Caulk and paint exterior of the home. Finish install of drywall in garage then tape and mud. Build shelves in laundry room closet. Caulk above kitchen cabinets and touch up paint. 8 5 03/17/2020
193485 - Tham Cleveland 3 Licensed electrician needs to inspect and replace any faulty wiring, licensed plumber needs to replace plumbing that has been removed and fix the new plumbing that has been done improperly. Furnace ductwork installed throughout house, house raised so that footings and pilings can be installed, install insulation under the floor, install missing floor joists at 16” on center through majority of house, install subfloor through entire house, install insulation in walls, hang drywall on walls (the muck out removed it up to 4’ but additional drywall has been removed up to the ceiling in places), install trim around windows, doors, and floor; install kitchen cabinets, and paint the drywall and trim. Homeowner has purchased all materials needed for repair. 6 15 12/02/2019
197061 - Swil Tulsa 3 Install 18 - 12 ft pieces of k-pattern stain grade trim for base and casing around doors. Apply one gallon of stain and poly and one gallon of white paint on the trim in the closets. Stain the new trim and touch up existing trim. Tools needed are finish nailer and a miter saw. Homeowner has SBA funding for materials. 3 2 01/06/2020
191129 - Roha Sand Springs 3 Install vinyl or laminate flooring, trim carpentry, install plumbing fixtures, cabinets and install outlets, switches and electrical fixtures. An experienced mason is needed to rebuild the brick in front of the fireplace. 2 2 01/06/2020
191050 - Rlin Moffett 3 Brace and support floor joist. Repair sub floor where needed. Install wall insulation into exterior walls. Hang drywall on interior walls. Repair skirt siding around house. Install 1x6 trim boards around windows and door front of house. Mud, tape, finish, and paint drywall. Install base molding. 01/09/2020
191050 - Esmi Moffett 3 Install insulation in exterior walls. Hang drywall on interior walls. Install plywood on floor joist for sub floor. Mud, tape, finish, and paint drywall. Install floor trim 01/09/2020
195369 - Rrai Barnsdall 3 Install 1x2 metal drip edge around outside edges of roof. Lay a bead of sealant under shingle side of the drip edge. Remove damage paneling between stove and front door. replace insulation water damaged, Hang drywall where needed. Has a small ceiling repair in bathroom, use drywall mud to texture as near as able. Spray Shockwave on any areas showing mold. Adjust front and back doors. 5 5 01/17/2020
199267 - Nvil Bixby 3 Once foundation contractor work is completed volunteers can make repairs to the bathroom. The toilet will need to be pulled and the subfloor replaced, new flange and wax ring installed and new vinyl plank flooring installed. Mold on the drywall around the toilet will need to be removed and remediated and replaced with mold resistance drywall, taped, textured, and painted. 3 3 02/04/2020
194450 - Eche Sapulpa 3 Home was damaged when a large tree 30+ inches in diameter fell onto the north side of the home. The tree compromised the decking near the edge of the roof and damaged about 3-4 rafters as well as the fascia. Inside the home in the living room the ceiling has started to fall in. The ceiling appears to be in two layers, one layer is sheetrock and one is ceiling tiles. Everything in the room will need to be moved out and the living room floor will need to be covered in preparation for the removal of the removal of both layers of the ceiling. Once ceiling is removed insulation will need to be stapled up to the rafters and the sheetrock installed, taped bedded and textured. The room is roughly 13x13. Once ceiling is taped, mudded and textured. It will need to be painted and the crown moulding installed. While the interior work is going on the exterior work can be worked on. On the exterior, shingles will need to be removed in order to replace the damaged rafters and decking. Once this is completed the fascia can be replaced and the shingles can be replaced. Paint fascia to match the existing color of the home. Roof will need to be accessed with a large extension ladder. Volunteer team will need wear proper PPE while removing ceiling. 6 3 02/24/2020
193728 - Wbea Sapulpa 4 Roof patch. Seal down loose shingles. 2 1 11/07/2019
194792 - Adba Moffett 4 Install ceiling and exterior insulation. Hang dry wall on interior walls and ceilings, Install sub floor where needed. Mud, tape, finish, and paint drywall. Install Laminate floor. Install 2 entry doors. 01/09/2020
190758 - Tjoh Sand Springs 4 Completion of interior stair trim. 01/17/2020
193881 - Dhaa Avant 4 Frame, insulate and reinstall skirting. Replace subfloor in kitchen, two bedrooms and closet. Replace flooring in kitchen, two bedrooms and closet. Contractor to level trailer 01/17/2020
199027 - Amcg Tulsa 4 All insulation in the basement ceiling will need to be removed and shockwave applied to the exposed subfloor and floor joist. The basement will also need to be power washed and cleaned of mud and other contents. Once the basement is prepped and dried out, insulation will need to be installed between floor joists and then covered with 6mm plastic sheething. Hydraulic cement needs to be applied to all cracks on the walls and floor. Once hydraulic cement has set the walls and floors will need to be coated with basement sealer. At least two coats need to be applied. 4 3 02/04/2020
191057 - Pand Yukon 4 Repair vinyl siding. Repair drywall in the hallway, kitchen and in an add on. Replace flooring in the hallway and bathroom. Contractor needs to level home. 10 7 02/17/2020
197804 - Cgra Oklahoma City 4 Install back door after contractor levels the home. 2 1 02/17/2020
198345 - Kbra Muskogee 4 Repair 8 x 8 bathroom ceiling with insulation and 1/4 plywood that needs to be removed and replaced and painted. Replace k-pattern trim installed as crown molding. Replace one section of drywall behind shower valve. Replace shower valve. Replace kitchen sink faucet. Work to be done after contractor replaces metal roof. 4 2 02/17/2020
190962 - Rall Skiatook 4 Remove and replace tile and drywall on walls in the bathroom and behind the shower replace hardie backer. Replace drywall in hotwater tank closet. Install kitchen cabinets, counter-tops, two exterior doors, four lights and 1 ceiling fan. Any evidence of mold will need to be removed and treated with mold inhibitor. 5 5 03/17/2020